Regulators in Wallonia and a Virginia judge halted two Google data center projects within days. Belgium cited a revoked water-cooling permit, while Virginia cited a breach of open-government law. Hearings in both places are scheduled for 2027.
Google has been ordered to stop construction twice in under a week, on two different continents. On Thursday, inspectors in Belgium's Wallonia region ordered about 300 workers off a Google data center site in Farciennes, near Charleroi. Three days earlier, a Virginia judge froze construction at a separate Google campus in Botetourt County.
Belgium: a revoked permit and continued building
The Belgian dispute centers on a 30,000 m² facility that was nearly finished when inspectors arrived. The core issue is a water-cooling permit, which was temporarily approved in April 2026 and revoked in August 2026. According to Wallonia's regional government, Google kept building after its amended permit was pulled.
Inspectors carried out the inspection on November 26-27, 2026, following evidence of compliance issues supplied by Greenpeace Belgium. Google said it had paused the work "pending additional guidance" and would seek clarity on its compliance obligations in Belgium.
Virginia: a deal approved outside open-government rules
The Virginia case has nothing to do with water. On November 23, 2026, a circuit court judge ruled that the performance agreement for Google's planned $3 billion data center in Botetourt County violated Virginia's Freedom of Information Act. The judge found that county supervisors broke the state's open-government law when they signed off on the arrangement.
Construction at the site had already started in September 2026. The ruling halted it, with only limited wind-down activity continuing.
Hearings set for 2027
The next formal checkpoint in Belgium is a Council of State hearing on the appeal, scheduled for January 7, 2027. It will show whether Google can save the Farciennes permit or has to change how the facility is cooled.
In Virginia, hearings are scheduled for early 2027, so neither project will get back to full speed quickly. If the deal is re-approved properly, the delay may be temporary.